Kayaş-Yerköy High-Speed Railway Project, Electrification, Signalling, and Telecommunication Systems Construction Work
The project encompasses the design, procurement, installation, testing, and commissioning of Electrification and Tunnel Electromechanical Systems, as well as Signalling, Communication, and Support Systems along the Kayaş-Yerköy route, spanning from KM 12+263 to KM 164+000.


The systems installed within the scope of electrification works of the project are as follows:
152 km double line catenary system suitable for 300+ % 10 km/h speed,
4 substations,
- Remote Control System (Scada System),
2 Km long single circuit, 477 MCM 154 kV Power Transmission Line,
10 Traction Post Buildings
PB Air Conditioning, Fire Detection and Burglar Alarm Systems,
Tunnel Grounding System.
The Project scope includes the following work items for Tunnel Electromechanics Systems:
Emergency Routing,
Tunnel Lighting and Emergency Lighting,
- Fire Detection and Fire Extinguishing,
TEM Building and Cabins.




The project scope includes the following work items for Signalling, Communication and Support Systems:
ERTMS/ETCS Level 1 and Level 2 Systems,
Electronic Interlocking,
CTC Command Center System,
- Wayside Signals,
Point Machine, Locking and Detection Systems
Point Heating System
- Track Circuits
Signal, Energy and FO Cables,
Power Supply Systems,
GSM-R System,
CTC System,
Telephony and Transmission (IP-MPLS) Systems,
Camera Security and Monitoring Systems (CCTV),
Earthquake Early Warning Systems,
15 units Signal Technical Buildings,
TB Air Conditioning, Fire Detection and Burglar Alarm Systems,
Wheel Detection Systems.